Civil Engineering Drawing Different Types Estimates Online Exam Quiz

Civil Engineering Drawing Different Types Estimates GK Quiz. Question and Answers related to Civil Engineering Drawing Different Types Estimates. MCQ (Multiple Choice Questions with answers about Civil Engineering Drawing Different Types Estimates

In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost.

Options

A : Annual repair

B : Item rate estimate

C : Approximate quantity method estimate

D : Cubical content estimate

View Answer

__________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.

Options

A : Cube Rate Estimate

B : Supplementary Estimate

C : Maintenance Estimate

D : Plinth Area Estimate

View Answer

Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared.

Options

A : False

B : True

C :

D :

View Answer

To make out an estimate for a work the following data are necessary-Drawing, Specification and ___________

Options

A : materials

B : rates

C : labours

D : transportation

View Answer

The term ______________ is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required.

Options

A : prime cost

B : hour-work

C : day-work

D : sub-work

View Answer

________________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.

Options

A : Prime cost

B : Provisional sum

C : Capital cost

D : Building cost index

View Answer

A large work or project may consists of several building or small works and each of these work is known as ___________

Options

A : sub-work

B : sub-project

C : sub-head

D : sub-construction

View Answer

_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.

Options

A : Supplementary and revised estimate

B : Maintenance estimate

C : Item rate estimate

D : Revised estimate

View Answer

_________________ is required for preliminary studies of various aspects of a work or project.

Options

A : Supplementary Estimate

B : Plinth Area Estimate

C : Revised Estimate

D : Abstract Estimate

View Answer

Approx. cost of a bridge of 3 spans of 50 m each span @Rs.30000/- per running m of span comes to 3*50*30000 = Rs. 45 lakhs.

Options

A : True

B : False

C :

D :

View Answer

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Civil Engineering Drawing Design Septic Tanks

Civil Engineering Drawing Detailed Specifications

Civil Engineering Drawing Detailed Specifications Road Work 1

Civil Engineering Drawing Developing Network

Civil Engineering Drawing Development Surfaces

Civil Engineering Drawing Earthwork Concrete R C C Work

Civil Engineering Drawing Earthwork Estimation

Civil Engineering Drawing Entrance Exams

Civil Engineering Drawing Estimate Metalled Roads

Civil Engineering Drawing Estimate Singledouble Room Building