Question: Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared.

Options

A : False

B : True

C :

D :

Click to view Correct Answer

Previous || Next

Civil Engineering Drawing Different Types Estimates more questions

Chowkhat shall be 7.5 cm* 7.5 cm of country wood....

Coke consumption can be reduced in the manufacture of pig....

Compounds can undergo hydrolysis with water.

Contractions of the myoepithelial cells eject milk.

Corrosion by seawater at greater depth is usually decreased because....

Depending on the configuration, 6 types of ovaries are present.

Depending on the source of pollen, pollination can be divided....

Dicots and monocots are types of seeds.

Diffusion-controlled oxidation can be minimized by decreasing the concentration of....

Drawing room should be light and ventilated and located in....

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Civil Engineering Drawing Design Septic Tanks

Civil Engineering Drawing Detailed Specifications

Civil Engineering Drawing Detailed Specifications Road Work 1

Civil Engineering Drawing Developing Network

Civil Engineering Drawing Development Surfaces

Civil Engineering Drawing Earthwork Concrete R C C Work

Civil Engineering Drawing Earthwork Estimation

Civil Engineering Drawing Entrance Exams

Civil Engineering Drawing Estimate Metalled Roads

Civil Engineering Drawing Estimate Singledouble Room Building