Question: ________________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.

Options

A : Prime cost

B : Provisional sum

C : Capital cost

D : Building cost index

Click to view Correct Answer

Previous || Next

Civil Engineering Drawing Different Types Estimates more questions

While estimating voltage regulation of a transformer, keeping ___________

What is the bar type current transformer?

What is the wound type current transformer?

In Rosetta, The segments with assigned _______ structures are subsequently....

The term ______________ is used to denote a procedure of....

If it is planned to bring an incoming alternator to....

Sum of two different prime number is a ____________

What is the number ‘ 1’?

In Vigenere method ______ is provided.

Which tool is used to remove dust from blast holes....

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Civil Engineering Drawing Design Septic Tanks

Civil Engineering Drawing Detailed Specifications

Civil Engineering Drawing Detailed Specifications Road Work 1

Civil Engineering Drawing Developing Network

Civil Engineering Drawing Development Surfaces

Civil Engineering Drawing Earthwork Concrete R C C Work

Civil Engineering Drawing Earthwork Estimation

Civil Engineering Drawing Entrance Exams

Civil Engineering Drawing Estimate Metalled Roads

Civil Engineering Drawing Estimate Singledouble Room Building