Question: The Overall in-charge of an organisation at the site responsible for the execution of the works, is
Options
A : Executive Engineer
B : Engineer
C : Junior Engineer
D : Sub overseer
Click to view Correct Answer
Construction Management - Part 1 more questions
If the total float and duration of an activity are....
Works costing less than Rs. 20,000 are treated as
The first method invented for planning projects, was
If TL is the latest allowable event occurrence time, total....
Modular co-ordination of construction means proper
According to the recommendations of International Navigational Congress in 1912,....
Pick up the correct statement from the following:
Flow of air from one place to the other is....