Question: If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

Options

A : LST-EST

B : LFT-EFT

C : TL-EFT

D : all the above.

Click to view Correct Answer

Previous || Next

Construction Management - Part 1 more questions

The time which results in the leasi, possible construction cost....

If the total float and duration of an activity are....

Works costing less than Rs. 20,000 are treated as

Bar charts are suitable for

The first method invented for planning projects, was

The Overall in-charge of an organisation at the site responsible....

Modular co-ordination of construction means proper

According to the recommendations of International Navigational Congress in 1912,....

Pick up the correct statement from the following:

The beach is built:

Advanced Surveying - Part 1 more Online Exam Quiz

Airport Engineering - Part 1

Applied Mechanics - Part 1

Building Construction - Part 1

Building Materials - Part 1

Concrete Technology - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1