Question: If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
Options
A : LST-EST
B : LFT-EFT
C : TL-EFT
D : all the above.
Click to view Correct Answer
Construction Management - Part 1 more questions
The time which results in the leasi, possible construction cost....
If the total float and duration of an activity are....
Works costing less than Rs. 20,000 are treated as
The first method invented for planning projects, was
The Overall in-charge of an organisation at the site responsible....
Modular co-ordination of construction means proper
According to the recommendations of International Navigational Congress in 1912,....
Pick up the correct statement from the following:
Advanced Surveying - Part 1 more Online Exam Quiz
Building Construction - Part 1
Elements of Remote Sensing - Part 1