Question: If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Options

A : started 5 days later

B : completed 5 days later

C : performed at slower rate in 15 days

D : all the above.

Click to view Correct Answer

Previous || Next

Construction Management - Part 1 more questions

Pick up the correct network for the activities of pouring....

Site order book is used for recording

An Executive Engineer may have powers upto

The estimated time required to perform an activity, is known....

The time which results in the leasi, possible construction cost....

Works costing less than Rs. 20,000 are treated as

Bar charts are suitable for

The first method invented for planning projects, was

If TL is the latest allowable event occurrence time, total....

The Overall in-charge of an organisation at the site responsible....

Advanced Surveying - Part 1 more Online Exam Quiz

Airport Engineering - Part 1

Applied Mechanics - Part 1

Building Construction - Part 1

Building Materials - Part 1

Concrete Technology - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1