Question: The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

Options

A : event

B : free float

C : dummy

D : constant

Click to view Correct Answer

Previous || Next

Construction Management - Part 1 more questions

Military organisation is known as

Pick up the incorrect statement from the following:

Various activities of a project, are shown on bar charts....

Critical Path Net Work helps an engineer

The time by which activity completion time can be delayed....

Henry Gantt developed Bar charts for planning and scheduling of....

The most popular type of organisation used for Civil Engineering....

The difference between the time avail-to do a job and....

Critical path lies along the activities having total float

Pick up the correct network for the activities of pouring....

Advanced Surveying - Part 1 more Online Exam Quiz

Airport Engineering - Part 1

Applied Mechanics - Part 1

Building Construction - Part 1

Building Materials - Part 1

Concrete Technology - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1