Question: The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

Options

A : duration

B : total flat

C : free float

D : interfering float.

Click to view Correct Answer

Previous || Next

Construction Management - Part 1 more questions

A dummy activity

Military organisation is known as

Pick up the incorrect statement from the following:

Various activities of a project, are shown on bar charts....

Critical Path Net Work helps an engineer

The artificial activity which indicates that an activity following it,....

Henry Gantt developed Bar charts for planning and scheduling of....

The most popular type of organisation used for Civil Engineering....

The difference between the time avail-to do a job and....

Critical path lies along the activities having total float

Advanced Surveying - Part 1 more Online Exam Quiz

Airport Engineering - Part 1

Applied Mechanics - Part 1

Building Construction - Part 1

Building Materials - Part 1

Concrete Technology - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1