Question: Critical Path Net Work helps an engineer
Options
A : to concentrate his attention on critical activities
B : to divert the resources from non-critical advanced activities to critical activities
C : to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D : all the above.
Construction Management - Part 1 more questions
Completion of an activity on CPM network diagram, is generally....
Military organisation is known as
Pick up the incorrect statement from the following:
Various activities of a project, are shown on bar charts....
The time by which activity completion time can be delayed....
The artificial activity which indicates that an activity following it,....
Henry Gantt developed Bar charts for planning and scheduling of....
The most popular type of organisation used for Civil Engineering....
The difference between the time avail-to do a job and....
Advanced Surveying - Part 1 more Online Exam Quiz
Building Construction - Part 1
Elements of Remote Sensing - Part 1