Question: Pick up the incorrect statement from the following:

Options

A : An activity of a project is denoted by an arrow on the net work

B : The tail of the arrow indicates the start of the activity

C : The head of the arrow indicates the end of the activity

D : The arrows are drawn to scale from left to right

Click to view Correct Answer

Next

Construction Management - Part 1 more questions

M 150 grade of concrete approximates

Workability of concrete is measured by

The rock which is not calcareous, is :

Internal friction between the ingredients of concrete, is decreased by....

For road pavements, the cement generally used, is

The technique for establishing and maintaining priorities among the various....

Mile Stone charts were invented in the year of

Frederick W. Taylor introduced a system of working known as

In the given figure, the network of a project represents

Final technical authority of a project lies with

Advanced Surveying - Part 1 more Online Exam Quiz

Airport Engineering - Part 1

Applied Mechanics - Part 1

Building Construction - Part 1

Building Materials - Part 1

Concrete Technology - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1