Question: Pick up the incorrect statement from the following:
Options
A : An activity of a project is denoted by an arrow on the net work
B : The tail of the arrow indicates the start of the activity
C : The head of the arrow indicates the end of the activity
D : The arrows are drawn to scale from left to right