Question: In the given figure, the network of a project represents

Options

A : activity of an excavation of a footing

B : activity of an excavation which starts at event No. 1 and ends at even No. 2

C : activity of excavation which takes 8 units of time

D : none of these.

Click to view Correct Answer

Previous || Next

Construction Management - Part 1 more questions

For road pavements, the cement generally used, is

Pick up the incorrect statement from the following:

The technique for establishing and maintaining priorities among the various....

Mile Stone charts were invented in the year of

Frederick W. Taylor introduced a system of working known as

Final technical authority of a project lies with

The performance of a specific task in CPM, is known

A Milestone chart

Completion of an activity on CPM network diagram, is generally....

A dummy activity

Advanced Surveying - Part 1 more Online Exam Quiz

Airport Engineering - Part 1

Applied Mechanics - Part 1

Building Construction - Part 1

Building Materials - Part 1

Concrete Technology - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1