Question: A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

Options

A : 26, 000 m 3

B : 26, 500 m 3

C : 27, 000 m 3

D : 27, 500 m 3

Click to view Correct Answer

Previous || Next

Estimating and Costing - Part 1 more questions

The project contractor relies on the cost of the estimate....

The wages of supervisors and material handlers are charged as....

The CRF (ep) is also known as: [CRF(EP) - 8%....

Pick up the excavation where measurements are made in square....

The expected out turn of 2.5 cm cement concrete floor....

The correct prismoidal formula for volume is

The order of booking dimensions is

As per Indian Standard Specifications, the peak discharge for domestic....

Pick up the correct statement from the following:

The brick work is measured in sq metre, in case....

Advanced Surveying - Part 1 more Online Exam Quiz

Concrete Technology - Part 1

Construction Management - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Engineering Economy - Part 1

GATE Exam Questions - Part 1

Highway Engineering - Part 1

Hydraulics - Part 1

Irrigation - Part 1

Railways - Part 1