Question: Pick up the correct reason for making conceptual (or preliminary) estimate from the following:
Options
A : To have a check on a definitive cost estimate.
B : To check qoutations from contractors and/or sub contractors.
C : To compute target estimate for the owner while drawings and specifications are in initial stage.
D : All of these.
Engineering Economy - Part 1 more questions
The interest calculated on the basis of 365 days a....
Each financial ratio is generally compared by
The key to profitable operation for project cost control, is....
The annuity which refers to a debt payment for recovering....
The product of CAF ( S P ) and PWF....
Pick up the correct statement from the following:
The project contractor relies on the cost of the estimate....
The wages of supervisors and material handlers are charged as....
The CRF (ep) is also known as: [CRF(EP) - 8%....
Pick up the excavation where measurements are made in square....
Advanced Surveying - Part 1 more Online Exam Quiz
Construction Management - Part 1
Elements of Remote Sensing - Part 1