Question: If a is the base amount expenditure, b is the increase in the operation cost each year over a period of n years, the total cost of maintenance is :

Options

A : a + ( n + 1) b

B : a + ( n - 1) b

C : a x ( n - 1) b

D : a - ( n - 1) b

Click to view Correct Answer

Previous || Next

Engineering Economy - Part 1 more questions

Which one of the following statements is correct?

The ratio of current assests to current liabilities is known....

Pick up the correct statement from the following:

The construction estimate of a project is used by :

Both architect and engineer make use of the cost estimate....

The more critical (or severe) test of the firm's liquidity....

Ratio analysis of a construction firm is used for analysis....

Probabilistic estimating of a construction project includes:

A construction estimate is used

Pick up the correct statement from the following:

Advanced Surveying - Part 1 more Online Exam Quiz

Building Materials - Part 1

Concrete Technology - Part 1

Construction Management - Part 1

Docks and Harbours - Part 1

Elements of Remote Sensing - Part 1

Estimating and Costing - Part 1

GATE Exam Questions - Part 1

Highway Engineering - Part 1

Hydraulics - Part 1

Irrigation - Part 1