Question: Which of the following is not a method used for preparing approximate estimates?

Options

A : Cubical contents method

B : Unit base method

C : Plinth area method

D : Cylindrical base method

Click to view Correct Answer

Previous || Next

Construction Cost Estimation Types Estimates more questions

The topological sorting of any DAG can be done in....

The unit cell with a?b?c and ?=?=90, ??90 refers to....

Which of the following is not a crystal system?

Which of the following transition-timing-function property lets you define your....

What is the general shape of an open riser?

An ideal sand should comprise of which of the following....

The shear stress distribution of I-section varies

Non-orthogonality leads to ________ in diffusion problems.

What is the shape of a tetrahedral element’s face?

Each face of a hexahedron is __________

Building Construction Question Papers more Online Exam Quiz

Computer Organization Questions Bank

Computer Organization Quiz

Computer Organization Test

Construction Building Materials Arches Technical Terms

Construction Cost Estimation Labour Rate Analysis

Construction Cost Estimation Units Dimensions

Construction Materials Aptitude Test

Construction Materials Assessment

Construction Materials Basic

Construction Materials Campus Interviews