Question: Power required during the open circuit and short circuit test is?

Options

A : losses incurring in the transformer

B : executing the power requirements by measuring instruments

C : power for the core losses only

D : all of the mentioned

Click to view Correct Answer

Previous || Next

Electrical Machines Open Circuit Short Circuit Test more questions

What is meant by passivation?

If the load angle is increased till 135°, the consequence....

What results in the use of a high degree of....

Which of the following lead to the bulged case of....

The rating of the alternator is decided by _________

Which achieves greater compression?

Which coding method uses entropy coding?

Wired channels are

Thermal noise is generated due to

Which of the following is first ever true collaboration platform?

Electrical Machines Action Commutator more Online Exam Quiz

Electrical Machines Mcqs

Electrical Machines Measurement Xd Xq

Electrical Machines Multiple Choice

Electrical Machines Online Quiz

Electrical Machines Online Test

Electrical Machines Operating Characteristics Dc Generator

Electrical Machines Operating Characteristics Dc Motor

Electrical Machines Operating Characteristics Induction Motors

Electrical Machines Permanent Magnet Dc Pmdc Motors

Electrical Machines Physical Concepts Synchronous Machine Operation