Question: ____________ is the clear vertical distance between the highest point on the intrados and springing line.

Options

A : Span

B : Rise

C : Arcade

D : Center

Click to view Correct Answer

Previous || Next

Construction Building Materials Arches Technical Terms more questions

Which of the following is not the right reason to....

Which method is better when traffic is heavy?

The bricks used for corners of walls of a structure....

Stones which are placed at regular interval right across the....

Which of the following is not an anti-spamming tool or....

The total operating range of the transducer is called __________

The horizontal distance between the internal faces of walls or....

Pitch is expressed as a ratio of _______

What is the maximum vertical deflection for a cantilever member....

What is the maximum vertical deflection in industrial building for....

Building Construction Interview Freshers more Online Exam Quiz

Computer Organization Online Quiz

Computer Organization Questions And Answers Interface Circuits

Computer Organization Questions Bank

Computer Organization Quiz

Computer Organization Test

Construction Cost Estimation Labour Rate Analysis

Construction Cost Estimation Types Estimates

Construction Cost Estimation Units Dimensions

Construction Materials Aptitude Test

Construction Materials Assessment