Question: In _______ type of bond, the brakes are laid on edge instead of bed.
Options
A : English cross bond
B : Brick on-edge bond
C : Raking bond
D : Dutch bond
Construction Building Materials Bonds Brickwork more questions
Which of the following is not considered while deciding the....
Inter-metallic corrosion between steel studs and aluminium alloy lead to....
What is the correct sequence of the coolant flow in....
In ___________ type of bond, all the brakes are arranged....
__________ bond is considered as the strongest Bond in brick....
In the ________ bond, one header course is provided after....
A context free grammar is a ___________
What does EGS stand for in geothermal energy?
Which among the following statements is false about background suppression?
PABA complex is used for the enhancement of ______________
Chemical Engineering Basics - Part 1 more Online Exam Quiz
Concrete Technology Water Proofing Admixtures
Concrete Technology Wet Process
Construction Building Materials Aptitude Test
Construction Building Materials Assessment
Construction Building Materials Basic
Construction Building Materials Bonds Connections
Construction Building Materials Campus Interviews
Construction Building Materials Characteristics Varnishing
Construction Building Materials Classification Caissons
Construction Building Materials Classification Stone Masonry