Question: In ___________ type of bond, all the brakes are arranged in the stretcher courses.

Options

A : English bond

B : Header bond

C : Stretcher bond

D : Flemish bond

Click to view Correct Answer

Previous || Next

Construction Building Materials Bonds Brickwork more questions

What happens if atmospheric temperature is too low?

Which among the following helps in the increase in the....

Which of the following is not considered while deciding the....

Inter-metallic corrosion between steel studs and aluminium alloy lead to....

What is the correct sequence of the coolant flow in....

__________ bond is considered as the strongest Bond in brick....

In _______ type of bond, the brakes are laid on....

In the ________ bond, one header course is provided after....

A context free grammar is a ___________

What does EGS stand for in geothermal energy?

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Concrete Technology Water Proofing Admixtures

Concrete Technology Wet Process

Construction Building Materials Aptitude Test

Construction Building Materials Assessment

Construction Building Materials Basic

Construction Building Materials Bonds Connections

Construction Building Materials Campus Interviews

Construction Building Materials Characteristics Varnishing

Construction Building Materials Classification Caissons

Construction Building Materials Classification Stone Masonry