Question: In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.

Options

A : 1-2

B : 5-9

C : 12-18

D : 16-20

Click to view Correct Answer

Next

Construction Cost Estimation Types Estimates more questions

Air contents should be _________ % by volume.

The pH of molasses solution in the manufacture of ethanol....

To reduce the feed flavor in milk to acceptable levels,....

What should be the range of oil/water partition coefficient of....

After vacuum mixing, the volumetric shrinkage can be raised from....

Fuels that congeal at ____________ degrees are used in automobiles.

How is much amount of chromium (in percent) normally added....

What is the formula for the window space factor, when....

Determine the resonant frequency of the circuit.

The rated current in induction motor for a three phase....

Building Construction Question Papers more Online Exam Quiz

Computer Organization Questions Bank

Computer Organization Quiz

Computer Organization Test

Construction Building Materials Arches Technical Terms

Construction Cost Estimation Labour Rate Analysis

Construction Cost Estimation Units Dimensions

Construction Materials Aptitude Test

Construction Materials Assessment

Construction Materials Basic

Construction Materials Campus Interviews