Question: How is the boxing of ballast done?

Options

A : Under the rails

B : At the rails

C : In between two rails

D : In between two sleepers

Click to view Correct Answer

Previous || Next

Civil Engineering Drawing Dealing Railways more questions

Backlash in a stable control system may cause:

Which of the mentioned below is not a type of....

On which condition does the vacuum advance mechanism shift the....

Compensating winding will provide incomplete neutralization ____________

To achieve high signal to noise ratio, delta modulation must....

The figure given below represents __________

Thermistor material is pressed ________

The thin layer of cement particles formed on excessive troweling....

In plastering, the 1st coat is called ___________ and its....

Which of the following is true regarding undercutting defect?

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Civil Engineering Drawing Classification Timber Carpenters Work

Civil Engineering Drawing Computer Aided Drafting

Civil Engineering Drawing Contract System

Civil Engineering Drawing Culverts

Civil Engineering Drawing Curves Used Engineering Practice

Civil Engineering Drawing Design Road Pavement

Civil Engineering Drawing Design Septic Tanks

Civil Engineering Drawing Detailed Specifications

Civil Engineering Drawing Detailed Specifications Road Work 1

Civil Engineering Drawing Developing Network