Question: Which one of the following is the most likely reason for large overshoot in a control system?

Options

A : High gain in a system

B : Presence of dead time delay in a system

C : High positive correcting torque

D : High retarding torque

Click to view Correct Answer

Previous || Next

Control System Experienced more questions

Which current is helpful in detecting surface breaking indication?

Ionospheric communication can take place in

The edges and other abrupt changes in gray-level of an....

What should be the frequency response of the amplifiers that....

Which of the following is not a reason for redistributing....

Which of the following anthracite coal is used in steel....

By which type of coal does briquettes are made?

Receptors dissociate from their bound ligands as a result of....

What type of Hydro plant is it if the Plant....

Which type of hydro plant is it if the head....

Control System Effect Adding Zero System Ii more Online Exam Quiz

Construction Materials Test

Construction Materials Types Paints

Construction Materials Types Pitched Roofs

Construction Materials Water Leakage

Control System Effect Adding Zero System Ii

Control System Experienced 2

Control System Frequency Response

Control System Interview Freshers

Control Systems Adaptive Controls

Control Systems All Pass Minimum Phase Systems