Question: The scale-up process is preferred to which condition?

Options

A : The migration of a process from the lab-scale to the pilot plant-scale

B : The migration of a process from the bench-scale to the lab-scale

C : The migration of a process from the small-scale to the lab-scale

D : The migration of a process from the bench-scale to the small-scale

Click to view Correct Answer

Previous || Next

Bioprocess Engineering Freshers more questions

Which of the following is untrue regarding dynamic programming algorithm?

Which of the given statements is incorrect about Ancient Conserved....

Which of these methods is not restricted to symmetric positive....

Which of the following is incorrect about the intramolecular approach?

Which phase is often referred to as the Green Revolution?

Which of these values is used to find the normalized....

What is the definition of a lower critical temperature?

What is pinch off voltage?

When performing subtraction by addition in the 2’s-complement system ____________

When performing subtraction by addition in the 2’s-complement system is?

Bioprocess Engineering Adsorption more Online Exam Quiz

Bioprocess Engineering External Mass Transfer

Bioprocess Engineering Factors Affecting Broth Viscosity

Bioprocess Engineering Fed Batch Culture

Bioprocess Engineering Filtration

Bioprocess Engineering Fluids Motion

Bioprocess Engineering Gene Therapy Using Viral Vectors

Bioprocess Engineering Ideal Reactor Operation

Bioprocess Engineering Internal Mass Transfer Reaction

Bioprocess Engineering Interview

Bioprocess Engineering Interview Experienced