Question: The detention period in a septic tank is assumed to be at _________
Options
A : 20 min
B : 30 min
C : 40 min
D : 25 min
Civil Engineering Drawing Masonry Platformwater Tankmotor Garage more questions
Calculate the velocity of the bottom point of the wheel....
What will be the value of i1 in the following....
A 4 bit modulo-16 ripple counter uses JK flip-flops. If....
What is the duration for memory refresh to remain compatible?
How many nucleosomes are present in a mammalian cell?
Every 100 ml deoxygenated blood delivers around _______ carbon dioxide....
Which of the following cannot be the thickness of a....
According to IRC:15-2002, Maximum nominal size of aggregates is ________
According to IRC:15-2011, Maximum nominal size of aggregates is ________
Begin the test by separating the grips at a speed....
Chemical Engineering Basics - Part 1 more Online Exam Quiz
Civil Engineering Drawing Labour Rates Workers
Civil Engineering Drawing Line Planned Storeyed Buildings
Civil Engineering Drawing Lines Lettering Dimensioning
Civil Engineering Drawing Loci Points
Civil Engineering Drawing Madras Terraced Sloping Roof
Civil Engineering Drawing Mcqs
Civil Engineering Drawing Measurement Calculation Quantities
Civil Engineering Drawing Mixed Masonry