Question: If t1=Time at which water is first added to cement, t2=Time when needle fails to penetrate 5 mm to 7 mm from bottom of the mould, t3=Time when the needle makes an impression but the attachment fails to do so, then what is final setting time?
Options
A : t2-t1
B : t2+t1
C : t3-t1
D : 2*t1
Concrete Technology Setting Time Test more questions
What is the formula to calculate the time taken for....
If T1 and T2 are two turing machines. The composite....
Which of the following viruses will be useful for transduction?
Which of the following is not a type of basic....
If t1=Time at which water is first added to cement,....
Which of the following is the largest bacteriophage?
Which of the mentioned below is the formula for calculating....
Which of the following can be done by shiny?
Which of the following property is used to specify table....
Which of the following content is allowed as per virtual....
Chemical Engineering Basics - Part 1 more Online Exam Quiz
Concrete Technology Questions Bank
Concrete Technology Ring Tension Test
Concrete Technology Road Method Mix Design
Concrete Technology Silica Fume
Concrete Technology Soundness Aggregates