Question: For walls, columns and vertical faces of all structural members, the form work is generally removed after __________

Options

A : 24 to 48 hours

B : 3 days

C : 7 days

D : 14 days

Click to view Correct Answer

Next

Concrete Technology Advantages Quality Control more questions

What is the humid heat of a mixture of air....

What is the generation time of a bacterial population that....

A triple –threaded screw is made 4 revolutions. What is....

The size of the marble chips used in terrazzo flooring....

If i1 = 3 cos(4t) and and i2 = 0.....

The total alumina content in high alumina cement should not....

Clay content in feebly hydraulic lime is about ________

What is the percentage composition of water in natural sands?

What is the maximum area of the rectangle with perimeter....

The mole percent of CO2 and H2O in a mixture....

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Computer Fundamentals Virtual Reality

Computer Fundamentals Waterfall Model

Computer Fundamentals Www

Concrete Technology Accelerators Retarders

Concrete Technology Admixtures

Concrete Technology Agents

Concrete Technology Aptitude Test

Concrete Technology Assessment

Concrete Technology Basic

Concrete Technology Bulking Aggregates