Question: For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is _________

Options

A : 0.190 m3

B : 0.230 m3

C : 0.174 m3

D : 0.274 m3

Click to view Correct Answer

Next

Civil Engineering Drawing Labour Rates Workers more questions

Determine V1 of the given network.

The coefficient of heat conductivity of heat-insulating materials does not....

What is the thickness of the layers of Class F....

The probability that there will be five or more murder....

A 4-pole Dc wound machine is lap wound with 400....

From the above equation, assuming the same values for the....

For an abrupt PN junction diode, small signal capacitance is....

Consider an abrupt PN junction. Let V0 be the built....

The built in capacitance V0 for a step graded PN....

The barrier layer capacitance of a point contact diode is_________

Chemical Engineering Basics - Part 1 more Online Exam Quiz

Civil Engineering Drawing Interview

Civil Engineering Drawing Interview Experienced

Civil Engineering Drawing Interview Freshers

Civil Engineering Drawing Isometric Projection

Civil Engineering Drawing Jack Arched Flat Terraced Roof

Civil Engineering Drawing Line Planned Storeyed Buildings

Civil Engineering Drawing Lines Lettering Dimensioning

Civil Engineering Drawing Loci Points

Civil Engineering Drawing Madras Terraced Sloping Roof

Civil Engineering Drawing Masonry Platformwater Tankmotor Garage