Question: According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as __________

Options

A : The most likely time estimate

B : Optimistic time estimate

C : Pessimistic time estimate

D : Expected time estimate

Click to view Correct Answer

Previous || Next

Building Construction Pert Cpm more questions

Which of the following is not similar between a first....

The direction of electric field in an LCD is determined....

The higher is the score in the alignment _________

Federal Milk Marketing Orders are a mechanism for?

Which of the following is incorrect regarding pair wise sequence....

In a family of four including a normal mother, a....

A child is born to a mother whose blood group....

If a mother has blood group O and father has....

Consider a DC generator running at the rated speed of....

What will happen if the back emf of a DC....

Building Construction Aptitude Test more Online Exam Quiz

Building Construction Multiple Choice

Building Construction Non Ferrous Metals Alloys 1

Building Construction Objective

Building Construction Online Quiz

Building Construction Online Test

Building Construction Plastics

Building Construction Question Papers

Building Construction Questions Bank

Building Construction Quiz

Building Construction Recommendations Indian Standard Code