Question: Probabilistic time for completion of any activity can be found out from
Options
A : optimistic time
B : pessimistic time
C : most likely time
D : all of these
Industrial Engineering and Production Management - Part 1 more questions
The procedure of modifying work content to give more meaning....
Fixed position layout is also known as
In a network shown in the below figure, the critical....
Which one of the following chart gives simultaneously information about....
Line organisation is suitable for a big organisation.
PERT is an event oriented technique.
Linear programming model can be applied to line balancing problem....
The chart which gives an estimate about the amount of....
The type of organisation preferred for a steel industry, is
Automobile Engineering - Part 1 more Online Exam Quiz
Engineering Mechanics - Part 1
Heat Transfer, Refrigeration and Air Conditioning - Part 1
Hydraulics and Fluid Mechanics - Part 1
IC Engines and Nuclear Power Plants - Part 1
Production Engineering - Part 1
Steam Boilers and Engines - Part 1