Question: When slack of an activity is negative

Options

A : it represents a situation where extra resources are available and the completion of project is not delayed

B : it represents that a programme falls behind schedule and additional resources are required to complete the project in time

C : the activity is critical and any delay in its performance will delay the completion of whole project

D : all of the above

Click to view Correct Answer

Previous || Next

Industrial Engineering and Production Management - Part 1 more questions

In inventory control theory, the economic order quantity is

Production cost refers to prime cost plus

A systematic job improvement sequence will consist of

Work sampling is applied for

Military type of organisation is known as

The procedure of modifying work content to give more meaning....

Fixed position layout is also known as

In a network shown in the below figure, the critical....

Bar chart is suitable for

Which one of the following chart gives simultaneously information about....

Automobile Engineering - Part 1 more Online Exam Quiz

Engineering Mechanics - Part 1

Heat Transfer, Refrigeration and Air Conditioning - Part 1

Hydraulic Machines - Part 1

Hydraulics and Fluid Mechanics - Part 1

IC Engines and Nuclear Power Plants - Part 1

Machine Design - Part 1

Production Engineering - Part 1

Steam Boilers and Engines - Part 1

Steam Nozzles and Turbines - Part 1

Theory of machines - Part 1