Question: When slack of an activity is negative
Options
A : it represents a situation where extra resources are available and the completion of project is not delayed
B : it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C : the activity is critical and any delay in its performance will delay the completion of whole project
D : all of the above
Industrial Engineering and Production Management - Part 1 more questions
In inventory control theory, the economic order quantity is
Production cost refers to prime cost plus
A systematic job improvement sequence will consist of
Military type of organisation is known as
The procedure of modifying work content to give more meaning....
Fixed position layout is also known as
In a network shown in the below figure, the critical....
Which one of the following chart gives simultaneously information about....
Automobile Engineering - Part 1 more Online Exam Quiz
Engineering Mechanics - Part 1
Heat Transfer, Refrigeration and Air Conditioning - Part 1
Hydraulics and Fluid Mechanics - Part 1
IC Engines and Nuclear Power Plants - Part 1
Production Engineering - Part 1
Steam Boilers and Engines - Part 1