Question: Gantt chart is used for

Options

A : inventory control

B : material handling

C : production schedule

D : machine repair schedules

Click to view Correct Answer

Previous || Next

Industrial Engineering and Production Management - Part 1 more questions

The nuclear power station at Tarapur has the reactor of....

In nuclear power plants, due to reflector, less fuel is....

The secondary fuel used in nuclear power plants is

The aim of value engineering is to

In time study, the rating factor is applied to determine

The main object of scientific layout is

In value engineering, the term value refers to

In inventory control theory, the economic order quantity is

Production cost refers to prime cost plus

A systematic job improvement sequence will consist of

Automobile Engineering - Part 1 more Online Exam Quiz

Engineering Mechanics - Part 1

Heat Transfer, Refrigeration and Air Conditioning - Part 1

Hydraulic Machines - Part 1

Hydraulics and Fluid Mechanics - Part 1

IC Engines and Nuclear Power Plants - Part 1

Machine Design - Part 1

Production Engineering - Part 1

Steam Boilers and Engines - Part 1

Steam Nozzles and Turbines - Part 1

Theory of machines - Part 1