Question: Which one of the following statements is not correct for heading and benching method of tunnelling ?

Options

A : Drilling and mucking can be done simultaneously

B : Benching provides a plateform for working on heading

C : Removal of muck from the heading is very easy

D : None of these.

Click to view Correct Answer

Next

Tunnelling - Part 1 more questions

If Q is load factor, S is shape factor and....

In plastic analysis, the shape factor for a triangular section,....

If ? H and ? V are the algebraic sums....

For determining the support reactions at A and B of....

Pick up the incorrect statement from the following : The....

The difference of heights of the tunnels above rail tops....

For B.G. single track railway, the height of the tunnel....

Pick up the correct statement regarding drilling a tunnel from....

For tunnels exceeding 300 m in length, the grade should....

The method of draining in the tunnels, is generally known....

Advanced Surveying - Part 1 more Online Exam Quiz

Steel Structure Design - Part 1

Strength of Materials - Part 1

Structural Design Specifications - Part 1

Surveying - Part 1

Theory of Structures - Part 1

UPSC Civil Service Exam Questions - Part 1

Waste Water Engineering - Part 1

Water Resources Engineering - Part 1

Water Supply Engineering - Part 1

Artificial Intelligence - Part 1