Question: Which one of the following statements is not correct for heading and benching method of tunnelling ?
Options
A : Drilling and mucking can be done simultaneously
B : Benching provides a plateform for working on heading
C : Removal of muck from the heading is very easy
D : None of these.
Tunnelling - Part 1 more questions
If Q is load factor, S is shape factor and....
In plastic analysis, the shape factor for a triangular section,....
If ? H and ? V are the algebraic sums....
For determining the support reactions at A and B of....
Pick up the incorrect statement from the following : The....
The difference of heights of the tunnels above rail tops....
For B.G. single track railway, the height of the tunnel....
Pick up the correct statement regarding drilling a tunnel from....
For tunnels exceeding 300 m in length, the grade should....
The method of draining in the tunnels, is generally known....
Advanced Surveying - Part 1 more Online Exam Quiz
Steel Structure Design - Part 1
Strength of Materials - Part 1
Structural Design Specifications - Part 1
UPSC Civil Service Exam Questions - Part 1
Waste Water Engineering - Part 1
Water Resources Engineering - Part 1