Question: A Milestone chart
Options
A : shows the interdependencies of various jobs
B : depicts the delay of jobs, if any
C : points outgoing ahead of schedule of jobs, if any
D : none of these.
Click to view Correct Answer
Construction Management - Part 1 more questions
Mile Stone charts were invented in the year of
Frederick W. Taylor introduced a system of working known as
In the given figure, the network of a project represents
Final technical authority of a project lies with
The performance of a specific task in CPM, is known
Completion of an activity on CPM network diagram, is generally....
Military organisation is known as
Pick up the incorrect statement from the following:
Various activities of a project, are shown on bar charts....
Advanced Surveying - Part 1 more Online Exam Quiz
Building Construction - Part 1
Elements of Remote Sensing - Part 1