Question: Which one of the following questions is relevant to the construction estimates :
Options
A : Did the estimators precisely evaluate site conditions ?
B : Did the estimators use short cut methods which may be un realistic in their situation ?
C : How much money will the contractor's risk, loosing if he Were to submit bid on the raw estimate of cost.
D : All of these
Engineering Economy - Part 1 more questions
The entire range of the electromagnetic spectrum spans a large....
Pick up the correct statement from the following :
A reduction of nitrogen nutrient in plants :
Pick up the correct statement from the following:
Leaf reflactance depends primarily on :
The ratio obtained by dividing 'quick assests' by current liabilities....
Which one of the following definitions, is correct ?
Pick up the element of the cost from the following:
The estimator for definitive estimates must be able :
Refer to the cash flow diagram of uniform gradient in....
Advanced Surveying - Part 1 more Online Exam Quiz
Construction Management - Part 1
Elements of Remote Sensing - Part 1